Road and Bridge Construction back to projects list »


2010 VMS FOUNDATION CONSTRUCTION SCHEME

The construction of 25 foundations for Variable Message Sign (VMS) gantries at locations on the National Road Network and ancillary works which involved Major Traffic Management installations at all Sites, Site Clearance Works, Site investigation Works and Accommodation Works including ducting and temporary works for the construction of these bases. The foundations for these Signs were based on two different sizes of signs i.e. MS 3 sign (7.0m * 5.0m) and MS 3 signs (2.5m * 2.0m).

2010 VMS FOUNDATION CONSTRUCTION SCHEME Project Team:
Client - National Roads Authority

Engineer - ARUP

Contract Value:
€ 479,650.17

Construction Period:
23rd August 2010 to 10th March 2011

2010 VMS FOUNDATION CONSTRUCTION SCHEME