JAMESON ROAD CELL 4 LINING WORKS
Construction of a new Landfill Cell with a containment area of 20,900m2
CONSTRUCTION ELEMENT INCLUDED
CONSTRUCTION OF CONTAINMENT BUND
Excavation of 4615m3 of stockpiled UA material and processing into suitable 2C material and placing in embankments to construct containment bund
ENGINEERED CLAY LINER
Import of 15,000m3 of engineering clay and placement of 700mm deep layer to form an
INSTALLATION OF PROTECTIVE HDPE FML LINER AND PROTECTIVE GEOTEXTILE
Installation of textured HDPE FML liner to full containment area including elements of extrusion welding and leak detection testing
Placement of two layers of Secutex 2002 protective geotextile over FML liner
INSTALLATION OF LEACHATE DRAINAGE AND EXTRACTION SYSTEM
1700m Dia. 225mm slotted HDPE pipes, butt welded
Construction of two leachate monitoring point pads and chambers and one leachate extraction pad and chamber
Placement of 7000m3 of leachate drainage stone on top of the protective geotextile layer
|
Project Team: Client - SITA UK Engineer - Terraconsult Ltd Contract Value: £805,595.08 Construction Period: 28th March 2011 - 9th September 2011 |