Landfill back to projects list »


JAMESON ROAD CELL 4 LINING WORKS

Construction of a new Landfill Cell with a containment area of 20,900m2

CONSTRUCTION ELEMENT INCLUDED

CONSTRUCTION OF CONTAINMENT BUND

Excavation of 4615m3 of stockpiled UA material and processing into suitable 2C material and placing in embankments to construct containment bund

ENGINEERED CLAY LINER

Import of 15,000m3 of engineering clay and placement of 700mm deep layer to form an

INSTALLATION OF PROTECTIVE HDPE FML LINER AND PROTECTIVE GEOTEXTILE

Installation of textured HDPE FML liner to full containment area including elements of extrusion welding and leak detection testing

Placement of two layers of Secutex 2002 protective geotextile over FML liner

INSTALLATION OF LEACHATE DRAINAGE AND EXTRACTION SYSTEM

1700m Dia. 225mm slotted HDPE pipes, butt welded

Construction of two leachate monitoring point pads and chambers and one leachate extraction pad and chamber

Placement of 7000m3 of leachate drainage stone on top of the protective geotextile layer

JAMESON ROAD CELL 4 LINING WORKS Project Team:
Client - SITA UK

Engineer - Terraconsult Ltd

Contract Value:
£805,595.08

Construction Period:
28th March 2011 - 9th September 2011